Step One: Collecting the material in a hopper or bin.
|
|
Step Two: Transport the raw material into the Martinater with a screw conveyor.
|
|
Step Three: Break/shredder the raw material with the Martinator (500 or 700) for opening the packaging.
|
|
|
|
Step Four: Transport the material into the Shop Return Press with a screw conveyor.
|
|
Step Five: Separate the packaging from the organic material by pressing the organic material out of the packaging. Clean organic material will be collected under the shop return press in a dripping pan. The removed packaging leaves the Shop Return Press at the end.
|
|
Step Six: Pumping the organic material into a storage tank or tank lorry, ready to be used in a biogas installation where eventually green electricity and warmth is created.
|
Step Seven: Collecting the removed packaging in a box or transporting the plastics with a screw conveyor into a container.
|
|